Project Challenge

Start up didn’t produce the Customer required quantity and rework level was a major challenge due to the high complexity.
 

Strategy Applied

Strategic problem solving for the top offenders using Shainin Red X complemented by Yellow Belt / A3 at each station, to resolve line stops.
 
Develop technology concept to significantly reduce rework time.
 
Introduction of Statistical Process Control per station to reduce process variation.
 

Implemented Results

FTQ (% of good parts produced ) improved from 0 to 50%, on plan to 70%.
 
Average rework time from 5h/part to below 15’.
 
Bottlenecks eliminated, no further delivery issue to Customer.
 